- SLIDE_COUNT: 2
- --- SLIDE1 TEXT FRAMES (up to 80) ---
- [0] ''
- [1] '六安裕洋MES项目实施进度汇报'
- [2] '京宜安 · 截至2026年7月21日 · 5–6月周任务64项已100%完成 · 本月聚焦现场培训/实际上线/陪产'
- [3] ''
- [4] '8周次'
- [5] '5–6月'
- [6] ''
- [7] '64/64'
- [8] '周任务完成'
- [9] ''
- [10] '100%'
- [11] '合格率'
- [12] ''
- [13] '7月'
- [14] '上线陪产'
- [15] ''
- [16] '周任务明细(阶段三~七 · 全部完成)'
- [17] ''
- [18] '阶段'
- [19] '起止'
- [20] '任务周'
- [21] '完成'
- [22] '合格率'
- [23] ''
- [24] '阶段三'
- [25] '5/7-5/10'
- [26] '五月第一周'
- [27] '8/8'
- [28] '100%'
- [29] ''
- [30] '阶段四'
- [31] '5/11-5/16'
- [32] '五月第二周'
- [33] '9/9'
- [34] '100%'
- [35] ''
- [36] '阶段四&五'
- [37] '5/18-5/23'
- [38] '五月第三周'
- [39] '9/9'
- [40] '100%'
- [41] ''
- [42] '阶段五'
- [43] '5/25-5/30'
- [44] '五月第四周'
- [45] '7/7'
- [46] '100%'
- [47] ''
- [48] '阶段六'
- [49] '6/1-6/6'
- [50] '六月第一周'
- [51] '7/7'
- [52] '100%'
- [53] ''
- [54] '阶段六'
- [55] '6/8-6/13'
- [56] '六月第二周'
- [57] '6/6'
- [58] '100%'
- [59] ''
- [60] '阶段六'
- [61] '6/13-6/18'
- [62] '六月第三周'
- [63] '10/10'
- [64] '100%'
- [65] ''
- [66] '阶段七'
- [67] '6/22-6/27'
- [68] '六月第四周'
- [69] '8/8'
- [70] '100%'
- [71] '合计:8 周次 · 任务 64 · 完成 64 · 合格率 100%'
- [72] ''
- [73] '实施阶段甘特图(2026-04-27 ~ 07-24)'
- [74] '今日 7/21'
- [75] ''
- [76] '4/27'
- [77] ''
- [78] '5/11'
- [79] ''
- --- STRING PRESENCE ---
- 周任务明细: True
- 本月重点: True
- 现场培训: True
- 实际上线: True
- 陪产: True
- 7月21: True
- 100%: True
- SLIDE2_PICTURE_COUNT: 8
|